Tenaga Listrik Gorontalo CFPP 100MW
- 2016년 2월 25일
- 1분 분량
Tenaga Listrik Gorontalo CFPP 100MW
25-Feb-2016
PNO.1312_18
Project Owner : PT. TLG (Electrical Plant Company)
Plant Type & Size : COAL FIRED POWER PLANT (12.5MW x 2)
Processing Method : IPP_CAPTIVE
Facility Location: Gorontalo Sulawesi
Business Permit Status : Approved
Purchase Price & Contract : 5.9Cents/Kwh (12.5MW x 2 facilities)
Raw material Supply Contract : LT Contract with current supplying company
B.P, E/S, F/S: B.P, E/S Completed, F/S in progress.
Project Description:
Currently 2 facilities of 12.5MW are in operation. Project type is IPP and has PPA with PLN and selling at 5.9Cents/Kwt since 2012. To further the project, we are trying to complete 100MW (50MW x 2) facilities by 2019 and in progress of building 2 single 100MW facilities by 2020.
Proposal:
The major shareholder (92.5% share) of the PT TLG (company currently operating this business) has plan to sell all of its shares and run for mayor of Jakarta, Indonesia..
- Share proportion of Major shareholder: 92.5%
- Family member (older brother) share proportion: 5%
- Share proportion of government owned company: 2.5%
Key Facts:
F/S completed in April, 2016
Project owner is (PT.TLG) “Brownfield” operating 2 facilities of 12.5MW
Operation type is IPP with PPA from PLN selling at 5.9 cents/Kwt
Plans to build 100MW (50MW x 2) by 2019 and expanding permit already received
lans to build 2 single facilities of 100MW by 2020
92.5% of shares to be sold at USD $35 million
Expecting to select EPC
Project owner wants Co-Developer to participate as a SI